A can complete a work in 20 days and B can complete the same work in 20 days. If they work together, in how many days will the work be completed? MCQ with Answer and Explanation

A can complete a work in 20 days and B can complete the same work in 20 days. If they work together, in how many days will the work be completed?
A. 16.0
B. 12.0
C. 10.0
D. 14.0
Answer: Option C
Solution (By JKSSB Mock Tests)
Combined rate = 1/20 + 1/20. Time = 1 ÷ combined rate = 10.0 days.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
16 men can complete a work in 14 days. If 20 men work at the same rate, in how many days will the work be completed?
A. 11.2
B. 13.2
C. 15.2
D. 17.2

Correct Answer: Option A


Explanation:
Total work = 16 × 14 = 224 man-days. Required days = 224/20 = 11.2 days.

This question belongs to: Maths Time and Work
Question #2
A can complete a work in 9 days and B in 24 days. If they work together, the work will be completed in:
A. 16.55
B. 11.55
C. 21.55
D. 6.55

Correct Answer: Option D


Explanation:
Combined rate = 1/9 + 1/24. Required time = 6.55 days.

This question belongs to: Maths Time and Work
Question #3
A can complete a work in 18 days. What percentage of work will A complete in 6 days?
A. 33.33
B. 38.33
C. 43.33
D. 48.33

Correct Answer: Option A


Explanation:
Percentage completed = (6/18) × 100 = 33.33%.

This question belongs to: Maths Time and Work