A can complete a work in 20 days and B in 40 days. After working together for 5 days, what percentage of work remains? MCQ with Answer and Explanation

A can complete a work in 20 days and B in 40 days. After working together for 5 days, what percentage of work remains?
A. 62.5
B. 65.0
C. 67.5
D. 70.0
Answer: Option A
Solution (By JKSSB Mock Tests)
Remaining work = (1 - 5*(1/20+1/40))×100 = 62.5%.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
A is twice as fast as B and B is twice as fast as C. If they together can complete a work in 4 days, in how many days can C alone complete it?
A. 24 days
B. 28 days
C. 16 days
D. 32 days

Correct Answer: Option B


Explanation:
Let efficiency of C = 1, then B = 2 and A = 4. Combined efficiency = 1 + 2 + 4 = 7 units/day. Total work = 4 * 7 = 28 units. Time taken by C alone = 28 / 1 = 28 days.

This question belongs to: Maths Time and Work
Question #2
12 men can complete a piece of work in 12 days. If 6 men leave after 6 days, how many more days will it take to complete the remaining work?
A. 6 days
B. 12 days
C. 8 days
D. 10 days

Correct Answer: Option B


Explanation:
Total work = 12 * 12 = 144 man-days. In 6 days, 12 men complete = 12 * 6 = 72 man-days. Remaining work = 144 - 72 = 72 man-days. Remaining men = 12 - 6 = 6 men. Time taken by 6 men to complete remaining work = 72 / 6 = 12 days.

This question belongs to: Maths Time and Work
Question #3
A can complete a work in 21 days and B can complete the same work in 16 days. If they work together, in how many days will the work be completed?
A. 13.08
B. 11.08
C. 9.08
D. 15.08

Correct Answer: Option C


Explanation:
Combined rate = 1/21 + 1/16. Time = 1 ÷ combined rate = 9.08 days.

This question belongs to: Maths Time and Work