Explanation:
3 Men = 4 Women => 1 Man = 4/3 Women. 7 men + 5 women = 7 * (4/3) + 5 = 28/3 + 5 = 43/3 women. Since 4 women take 43 days, 43/3 women will take (4 * 43) / (43/3) = 4 * 3 = 12 days.
Explanation:
Let efficiency of B = 1, then efficiency of A = 2. Combined efficiency = 3 units/day. Total work = 8 * 3 = 24 units. Time taken by A alone = 24 / 2 = 12 days.