A can complete a work in 21 days and B in 42 days. After working together for 5 days, what percentage of work remains? MCQ with Answer and Explanation

A can complete a work in 21 days and B in 42 days. After working together for 5 days, what percentage of work remains?
A. 69.29
B. 71.79
C. 66.79
D. 64.29
Answer: Option D
Solution (By JKSSB Mock Tests)
Remaining work = (1 - 5*(1/21+1/42))×100 = 64.29%.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
A is twice as fast as B. If A and B together can complete a piece of work in 8 days, in how many days can A alone complete it?
A. 16 days
B. 10 days
C. 12 days
D. 24 days

Correct Answer: Option C


Explanation:
Let efficiency of B = 1, then efficiency of A = 2. Combined efficiency = 3 units/day. Total work = 8 * 3 = 24 units. Time taken by A alone = 24 / 2 = 12 days.

This question belongs to: Maths Time and Work
Question #2
A can complete a work in 24 days and B can complete the same work in 24 days. If they work together, in how many days will the work be completed?
A. 16.0
B. 14.0
C. 12.0
D. 18.0

Correct Answer: Option C


Explanation:
Combined rate = 1/24 + 1/24. Time = 1 ÷ combined rate = 12.0 days.

This question belongs to: Maths Time and Work
Question #3
18 men can complete a work in 16 days. If 22 men work at the same rate, in how many days will the work be completed?
A. 15.09
B. 17.09
C. 19.09
D. 13.09

Correct Answer: Option D


Explanation:
Total work = 18 × 16 = 288 man-days. Required days = 288/22 = 13.09 days.

This question belongs to: Maths Time and Work