A can complete a work in 22 days. What percentage of work will A complete in 6 days?
A. 37.27
B. 27.27
C. 42.27
D. 32.27
Answer: Option B
Solution (By JKSSB Mock Tests)
Percentage completed = (6/22) × 100 = 27.27%.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
A can complete a work in 10 days and B can complete the same work in 30 days. If they work together, in how many days will the work be completed?
A. 9.5
B. 11.5
C. 7.5
D. 13.5

Correct Answer: Option C


Explanation:
Combined rate = 1/10 + 1/30. Time = 1 ÷ combined rate = 7.5 days.

This question belongs to: Maths Time and Work
Question #2
A can complete a work in 16 days and B can complete the same work in 21 days. If they work together, in how many days will the work be completed?
A. 15.08
B. 11.08
C. 13.08
D. 9.08

Correct Answer: Option D


Explanation:
Combined rate = 1/16 + 1/21. Time = 1 ÷ combined rate = 9.08 days.

This question belongs to: Maths Time and Work
Question #3
8 men can complete a work in 12 days. If 12 men work at the same rate, in how many days will the work be completed?
A. 14.0
B. 12.0
C. 8.0
D. 10.0

Correct Answer: Option C


Explanation:
Total work = 8 × 12 = 96 man-days. Required days = 96/12 = 8.0 days.