A can complete a work in 23 days and B in 46 days. After working together for 5 days, what percentage of work remains? MCQ with Answer and Explanation

A can complete a work in 23 days and B in 46 days. After working together for 5 days, what percentage of work remains?
A. 69.89
B. 74.89
C. 72.39
D. 67.39
Answer: Option D
Solution (By JKSSB Mock Tests)
Remaining work = (1 - 5*(1/23+1/46))×100 = 67.39%.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
A can do a piece of work in 10 days and B can do the same work in 15 days. If they work together, in how many days will the work be completed?
A. 6 days
B. 5 days
C. 8 days
D. 9 days

Correct Answer: Option A


Explanation:
A's 1-day work = 1/10, B's 1-day work = 1/15. Combined 1-day work = 1/10 + 1/15 = 5/30 = 1/6. Therefore, they will complete the work together in 6 days.

This question belongs to: Maths Time and Work
Question #2
A can complete a work in 11 days and B can complete the same work in 26 days. If they work together, in how many days will the work be completed?
A. 13.73
B. 11.73
C. 7.73
D. 9.73

Correct Answer: Option C


Explanation:
Combined rate = 1/11 + 1/26. Time = 1 ÷ combined rate = 7.73 days.

This question belongs to: Maths Time and Work
Question #3
14 men can complete a work in 18 days. If 18 men work at the same rate, in how many days will the work be completed?
A. 14.0
B. 16.0
C. 18.0
D. 20.0

Correct Answer: Option A


Explanation:
Total work = 14 × 18 = 252 man-days. Required days = 252/18 = 14.0 days.

This question belongs to: Maths Time and Work