A can complete a work in 26 days and B in 52 days. After working together for 5 days, what percentage of work remains? MCQ with Answer and Explanation

A can complete a work in 26 days and B in 52 days. After working together for 5 days, what percentage of work remains?
A. 78.65
B. 71.15
C. 76.15
D. 73.65
Answer: Option B
Solution (By JKSSB Mock Tests)
Remaining work = (1 - 5*(1/26+1/52))×100 = 71.15%.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
A and B work together. A alone can complete the work in 24 days and B alone in 26 days. What percentage of the total daily work is contributed by A?
A. 54.5
B. 52.0
C. 59.5
D. 57.0

Correct Answer: Option B


Explanation:
A share = (1/24) / (1/24+1/26) ×100 = 52.0%.

This question belongs to: Maths Time and Work
Question #2
A can do a work in 15 days and B in 29 days. In how many days will they complete 75% of the work together?
A. 7.41
B. 12.41
C. 9.91
D. 14.91

Correct Answer: Option A


Explanation:
Combined time for full work multiplied by 0.75 = 7.41 days.

This question belongs to: Maths Time and Work
Question #3
A can complete a work in 16 days and B can complete the same work in 16 days. If they work together, in how many days will the work be completed?
A. 14.0
B. 8.0
C. 10.0
D. 12.0

Correct Answer: Option B


Explanation:
Combined rate = 1/16 + 1/16. Time = 1 ÷ combined rate = 8.0 days.