A can do a work in 11 days and B in 23 days. In how many days will they complete 75% of the work together? MCQ with Answer and Explanation

A can do a work in 11 days and B in 23 days. In how many days will they complete 75% of the work together?
A. 8.08
B. 13.08
C. 5.58
D. 10.58
Answer: Option C
Solution (By JKSSB Mock Tests)
Combined time for full work multiplied by 0.75 = 5.58 days.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
A is 40% more efficient than B. If they together can finish a work in 10 days, in how many days can A alone finish it?
A. 17(1/7) days
B. 15 days
C. 14 days
D. 16(2/3) days

Correct Answer: Option A


Explanation:
Let efficiency of B = 5, then efficiency of A = 7. Combined efficiency = 12 units/day. Total work = 10 * 12 = 120 units. Time taken by A alone = 120 / 7 = 17(1/7) days.

This question belongs to: Maths Time and Work
Question #2
A can do a work in 9 days and B in 23 days. In how many days will they complete 75% of the work together?
A. 4.85
B. 7.35
C. 12.35
D. 9.85

Correct Answer: Option A


Explanation:
Combined time for full work multiplied by 0.75 = 4.85 days.

This question belongs to: Maths Time and Work
Question #3
A can complete a work in 21 days and B in 25 days. If they work together, the work will be completed in:
A. 16.41
B. 11.41
C. 26.41
D. 21.41

Correct Answer: Option B


Explanation:
Combined rate = 1/21 + 1/25. Required time = 11.41 days.