A can do a work in 4 days, B in 5 days and C in 10 days. Find the time taken by A, B and C together to do the work. MCQ with Answer and Explanation

A can do a work in 4 days, B in 5 days and C in 10 days. Find the time taken by A, B and C together to do the work.
A. 1(9/11) days
B. 2(1/11) days
C. 1(7/11) days
D. 2 days
Answer: Option A
Solution (By JKSSB Mock Tests)
Total work = LCM(4, 5, 10) = 20 units. Efficiency of A = 5, B = 4, C = 2. Combined efficiency = 5 + 4 + 2 = 11 units/day. Time taken together = 20 / 11 = 1(9/11) days.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
A can complete a project in 20 days and B in 30 days. If they work on alternate days starting with A, in how many days will the project be completed?
A. 26 days
B. 25 days
C. 24 days
D. 22 days

Correct Answer: Option C


Explanation:
Total work = LCM(20, 30) = 60 units. Efficiency of A = 3, B = 2. In a 2-day cycle (A then B), work completed = 3 + 2 = 5 units. Number of cycles required = 60 / 5 = 12 cycles. Total time = 12 * 2 = 24 days.

This question belongs to: Maths Time and Work
Question #2
A can complete a work in 34 days and B in 38 days. If both work together, in how many days will the work be completed?
A. 17.94
B. 25.44
C. 22.94
D. 20.44

Correct Answer: Option A


Explanation:
Combined rate = 1/34 + 1/38. Time = 17.94 days.

This question belongs to: Maths Time and Work
Question #3
A is twice as efficient as B, and C is thrice as efficient as B. If they working together can finish a work in 5 days, in how many days can A alone finish it?
A. 10 days
B. 12 days
C. 18 days
D. 15 days

Correct Answer: Option D


Explanation:
Let efficiency of B = 1. Then efficiency of A = 2, and efficiency of C = 3. Combined efficiency = 1 + 2 + 3 = 6. Total work = 5 * 6 = 30 units. Time taken by A alone = 30 / 2 = 15 days.

This question belongs to: Maths Time and Work