A work could be completed in 100 days by some workers. However, due to the absence of 10 workers, it was completed in 110 days. Find the original number of workers. MCQ with Answer and Explanation
A work could be completed in 100 days by some workers. However, due to the absence of 10 workers, it was completed in 110 days. Find the original number of workers.
A. 55
B. 100
C. 110
D. 120
Answer: Option C
Solution (By JKSSB Mock Tests)
Let the original number of workers be x. Using M1 * D1 = M2 * D2: x * 100 = (x - 10) * 110 => 100x = 110x - 1100 => 10x = 1100 => x = 110.
A and B can complete a work in 12 days and 16 days respectively. Both work together for 3 days and then A leaves. How long will B take to complete the remaining work?
Explanation:
Total work = LCM(12, 16) = 48 units. Efficiency of A = 4, B = 3. Combined efficiency = 7 units/day. In 3 days, work completed = 3 * 7 = 21 units. Remaining work = 48 - 21 = 27 units. Time taken by B to complete remaining work = 27 / 3 = 9 days.