If 12 men or 18 women can reap a field in 14 days, then the number of days that 8 men and 16 women will take to reap it is: MCQ with Answer and Explanation

If 12 men or 18 women can reap a field in 14 days, then the number of days that 8 men and 16 women will take to reap it is:
A. 7 days
B. 9 days
C. 10 days
D. 8 days
Answer: Option B
Solution (By JKSSB Mock Tests)
12 Men = 18 Women => 1 Man = 1.5 Women. 8 men + 16 women = 8 * 1.5 + 16 = 12 + 16 = 28 women. Since 18 women take 14 days, 28 women will take (18 * 14) / 28 = 252 / 28 = 9 days.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
23 men can complete a work in 26 days. If 31 men work at the same rate, how many days are required?
A. 24.29
B. 19.29
C. 21.79
D. 26.79

Correct Answer: Option B


Explanation:
Total work = 598 man-days. Days = 19.29.

This question belongs to: Maths Time and Work
Question #2
A is 50% more efficient than B. If A can complete a piece of work in 12 days, in how many days can B complete the same work?
A. 24 days
B. 15 days
C. 18 days
D. 20 days

Correct Answer: Option C


Explanation:
Let efficiency of B = 2, then efficiency of A = 3. Total work = Efficiency of A * Time of A = 3 * 12 = 36 units. Time taken by B = 36 / 2 = 18 days.

This question belongs to: Maths Time and Work
Question #3
A can complete a work in 17 days and B can complete the same work in 32 days. If they work together, in how many days will the work be completed?
A. 11.1
B. 15.1
C. 13.1
D. 17.1

Correct Answer: Option A


Explanation:
Combined rate = 1/17 + 1/32. Time = 1 ÷ combined rate = 11.1 days.

This question belongs to: Maths Time and Work