If 12 men or 18 women can reap a field in 14 days, then the number of days that 8 men and 16 women will take to reap it is: MCQ with Answer and Explanation

If 12 men or 18 women can reap a field in 14 days, then the number of days that 8 men and 16 women will take to reap it is:
A. 7 days
B. 9 days
C. 8 days
D. 10 days
Answer: Option B
Solution (By JKSSB Mock Tests)
12 Men = 18 Women => 1 Man = 1.5 Women. 8 men + 16 women = 8 * 1.5 + 16 = 12 + 16 = 28 women. Since 18 women take 14 days, 28 women will take (18 * 14) / 28 = 252 / 28 = 9 days.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
A and B can complete a work in 10 days and 15 days respectively. They started together, but A left after some days and B finished the remaining work in 5 days. After how many days did A leave?
A. 3 days
B. 2 days
C. 5 days
D. 4 days

Correct Answer: Option D


Explanation:
Total work = LCM(10, 15) = 30 units. Efficiency of A = 3, B = 2. B worked alone for 5 days: work done = 5 * 2 = 10 units. Remaining work = 30 - 10 = 20 units. This was completed by A and B together. Combined efficiency = 3 + 2 = 5 units/day. Time they worked together = 20 / 5 = 4 days. Thus, A left after 4 days.

This question belongs to: Maths Time and Work
Question #2
A can complete a work in 22 days. What percentage of work will A complete in 6 days?
A. 37.27
B. 27.27
C. 32.27
D. 42.27

Correct Answer: Option B


Explanation:
Percentage completed = (6/22) × 100 = 27.27%.

This question belongs to: Maths Time and Work
Question #3
A is 50% more efficient than B. If A can complete a piece of work in 12 days, in how many days can B complete the same work?
A. 18 days
B. 24 days
C. 15 days
D. 20 days

Correct Answer: Option A


Explanation:
Let efficiency of B = 2, then efficiency of A = 3. Total work = Efficiency of A * Time of A = 3 * 12 = 36 units. Time taken by B = 36 / 2 = 18 days.

This question belongs to: Maths Time and Work