X can do a piece of work in 24 days. When he had worked for 4 days, Y joined him. If complete work was finished in 14 days, Y alone can finish that work in: MCQ with Answer and Explanation

X can do a piece of work in 24 days. When he had worked for 4 days, Y joined him. If complete work was finished in 14 days, Y alone can finish that work in:
A. 20 days
B. 18 days
C. 30 days
D. 24 days
Answer: Option D
Solution (By JKSSB Mock Tests)
Let total work be 24 units. Efficiency of X = 1 unit/day. X worked for all 14 days, so work done by X = 14 * 1 = 14 units. Remaining work = 24 - 14 = 10 units. This 10 units of work was done by Y. Y worked for 14 - 4 = 10 days. So Y's efficiency = 10 / 10 = 1 unit/day. Time taken by Y alone = 24 / 1 = 24 days.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
A can complete a work in 20 days and B can complete the same work in 25 days. If they work together, in how many days will the work be completed?
A. 13.11
B. 11.11
C. 15.11
D. 17.11

Correct Answer: Option B


Explanation:
Combined rate = 1/20 + 1/25. Time = 1 ÷ combined rate = 11.11 days.

This question belongs to: Maths Time and Work
Question #2
A can complete a work in 16 days and B in 18 days. If they work together, the work will be completed in:
A. 18.47
B. 23.47
C. 8.47
D. 13.47

Correct Answer: Option C


Explanation:
Combined rate = 1/16 + 1/18. Required time = 8.47 days.

This question belongs to: Maths Time and Work
Question #3
A can complete a work in 10 days and B in 30 days. If they work together, the work will be completed in:
A. 17.5
B. 12.5
C. 22.5
D. 7.5

Correct Answer: Option D


Explanation:
Combined rate = 1/10 + 1/30. Required time = 7.5 days.