12 men can complete a piece of work in 36 days. In how many days will 18 men complete the same work? MCQ with Answer and Explanation

12 men can complete a piece of work in 36 days. In how many days will 18 men complete the same work?
A. 24 days
B. 18 days
C. 28 days
D. 30 days
Answer: Option A
Solution (By JKSSB Mock Tests)
Using M1 * D1 = M2 * D2: 12 * 36 = 18 * D2 => D2 = (12 * 36) / 18 = 12 * 2 = 24 days.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
A can do a piece of work in 24 days and B in 30 days. They work together for 6 days and then A leaves. How many days will B take to complete the remaining work?
A. 15 days
B. 14 days
C. 18.5 days
D. 16.5 days

Correct Answer: Option D


Explanation:
Total work = LCM(24, 30) = 120 units. Efficiency of A = 5, B = 4. Combined efficiency = 9. In 6 days, work done = 6 * 9 = 54 units. Remaining work = 120 - 54 = 66 units. Time taken by B to complete the remaining work = 66 / 4 = 16.5 days.

This question belongs to: Maths Time and Work
Question #2
A can do a piece of work in 15 days and B in 20 days. They began the work together but A left after 4 days. In how many days will B complete the remaining work?
A. 10(1/3) days
B. 9(1/3) days
C. 8 days
D. 10(2/3) days

Correct Answer: Option D


Explanation:
Total work = LCM(15, 20) = 60 units. Efficiency of A = 4, B = 3. Combined efficiency = 7. In 4 days, work completed = 4 * 7 = 28 units. Remaining work = 60 - 28 = 32 units. Time taken by B to complete remaining work = 32 / 3 = 10(2/3) days.

This question belongs to: Maths Time and Work
Question #3
A and B work together. A alone can complete the work in 18 days and B alone in 30 days. What percentage of the total daily work is contributed by A?
A. 67.5
B. 70.0
C. 62.5
D. 65.0

Correct Answer: Option C


Explanation:
A share = (1/18) / (1/18+1/30) ×100 = 62.5%.

This question belongs to: Maths Time and Work