A can do a piece of work in 24 days and B in 30 days. They work together for 6 days and then A leaves. How many days will B take to complete the remaining work?
A. 18.5 days
B. 16.5 days
C. 15 days
D. 14 days
Answer: Option B
Solution (By JKSSB Mock Tests)
Total work = LCM(24, 30) = 120 units. Efficiency of A = 5, B = 4. Combined efficiency = 9. In 6 days, work done = 6 * 9 = 54 units. Remaining work = 120 - 54 = 66 units. Time taken by B to complete the remaining work = 66 / 4 = 16.5 days.