13 men can complete a work in 17 days. If 17 men work at the same rate, in how many days will the work be completed? MCQ with Answer and Explanation

13 men can complete a work in 17 days. If 17 men work at the same rate, in how many days will the work be completed?
A. 15.0
B. 17.0
C. 13.0
D. 19.0
Answer: Option C
Solution (By JKSSB Mock Tests)
Total work = 13 × 17 = 221 man-days. Required days = 221/17 = 13.0 days.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
A can do a certain work in the same time in which B and C together can do it. If A and B together could do it in 10 days and C alone in 50 days, then B alone could do it in:
A. 25 days
B. 30 days
C. 20 days
D. 35 days

Correct Answer: Option A


Explanation:
Total work = LCM(10, 50) = 50 units. Efficiency of (A + B) = 5, efficiency of C = 1. Total efficiency of (A + B + C) = 5 + 1 = 6. Given A = B + C. So, (B + C) + B + C = 6 => 2(B + C) = 6 => B + C = 3. Since C = 1, B = 2. Time taken by B alone = 50 / 2 = 25 days.

This question belongs to: Maths Time and Work
Question #2
A can complete a work in 22 days and B in 33 days. If both work together, in how many days will the work be completed?
A. 20.7
B. 18.2
C. 13.2
D. 15.7

Correct Answer: Option C


Explanation:
Combined rate = 1/22 + 1/33. Time = 13.2 days.

This question belongs to: Maths Time and Work
Question #3
A can do a work in 18 days and B in 24 days. They start together but A leaves 3 days before the completion of the work. Find the total number of days taken to complete the work.
A. 13 days
B. 12 days
C. 10 days
D. 11 days

Correct Answer: Option B


Explanation:
Total work = LCM(18, 24) = 72 units. Efficiency of A = 4, B = 3. Let total days be x. A works for (x - 3) days, B works for x days. 4(x - 3) + 3x = 72 => 4x - 12 + 3x = 72 => 7x = 84 => x = 12 days.

This question belongs to: Maths Time and Work