15 men can complete a work in 13 days. If 19 men work at the same rate, in how many days will the work be completed? MCQ with Answer and Explanation

15 men can complete a work in 13 days. If 19 men work at the same rate, in how many days will the work be completed?
A. 12.26
B. 10.26
C. 16.26
D. 14.26
Answer: Option B
Solution (By JKSSB Mock Tests)
Total work = 15 × 13 = 195 man-days. Required days = 195/19 = 10.26 days.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
A and B work together. A alone can complete the work in 24 days and B alone in 34 days. What percentage of the total daily work is contributed by A?
A. 58.62
B. 66.12
C. 61.12
D. 63.62

Correct Answer: Option A


Explanation:
A share = (1/24) / (1/24+1/34) ×100 = 58.62%.

This question belongs to: Maths Time and Work
Question #2
A and B work together. A alone can complete the work in 30 days and B alone in 22 days. What percentage of the total daily work is contributed by A?
A. 42.31
B. 47.31
C. 49.81
D. 44.81

Correct Answer: Option A


Explanation:
A share = (1/30) / (1/30+1/22) ×100 = 42.31%.

This question belongs to: Maths Time and Work
Question #3
A and B work together. A alone can complete the work in 30 days and B alone in 36 days. What percentage of the total daily work is contributed by A?
A. 62.05
B. 57.05
C. 59.55
D. 54.55

Correct Answer: Option D


Explanation:
A share = (1/30) / (1/30+1/36) ×100 = 54.55%.

This question belongs to: Maths Time and Work