15 men can complete a work in 19 days. If 19 men work at the same rate, in how many days will the work be completed?
A. 15.0
B. 21.0
C. 19.0
D. 17.0
Answer: Option A
Solution (By JKSSB Mock Tests)
Total work = 15 × 19 = 285 man-days. Required days = 285/19 = 15.0 days.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
A can complete a work in 19 days and B in 19 days. If both work together, in how many days will the work be completed?
A. 9.5
B. 17.0
C. 12.0
D. 14.5

Correct Answer: Option A


Explanation:
Combined rate = 1/19 + 1/19. Time = 9.5 days.

This question belongs to: Maths Time and Work
Question #2
A is 50% more efficient than B. If A can complete a piece of work in 12 days, in how many days can B complete the same work?
A. 20 days
B. 18 days
C. 24 days
D. 15 days

Correct Answer: Option B


Explanation:
Let efficiency of B = 2, then efficiency of A = 3. Total work = Efficiency of A * Time of A = 3 * 12 = 36 units. Time taken by B = 36 / 2 = 18 days.

This question belongs to: Maths Time and Work
Question #3
15 men can complete a work in 25 days. If 19 men work at the same rate, in how many days will the work be completed?
A. 25.74
B. 21.74
C. 19.74
D. 23.74

Correct Answer: Option C


Explanation:
Total work = 15 × 25 = 375 man-days. Required days = 375/19 = 19.74 days.