A and B work together. A alone can complete the work in 24 days and B alone in 26 days. What percentage of the total daily work is contributed by A? MCQ with Answer and Explanation

A and B work together. A alone can complete the work in 24 days and B alone in 26 days. What percentage of the total daily work is contributed by A?
A. 52.0
B. 57.0
C. 54.5
D. 59.5
Answer: Option A
Solution (By JKSSB Mock Tests)
A share = (1/24) / (1/24+1/26) ×100 = 52.0%.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
12 men can complete a work in 4 days, while 15 women can complete the same work in 4 days. 6 men start working and after 2 days, all of them stop working. How many women should be put on the job to complete the remaining work in 3 days?
A. 15
B. 18
C. 25
D. 20

Correct Answer: Option A


Explanation:
Total work = 12M * 4 = 48 man-days = 15W * 4 = 60 woman-days. So, 48M = 60W => 4M = 5W => 1M = 1.25W. Work done by 6 men in 2 days = 12 man-days. Remaining work = 48 - 12 = 36 man-days. Converting to woman-days: 36 * 1.25 = 45 woman-days. To complete 45 woman-days in 3 days, number of women required = 45 / 3 = 15 women.

This question belongs to: Maths Time and Work
Question #2
A and B work together. A alone can complete the work in 24 days and B alone in 32 days. What percentage of the total daily work is contributed by A?
A. 62.14
B. 64.64
C. 57.14
D. 59.64

Correct Answer: Option C


Explanation:
A share = (1/24) / (1/24+1/32) ×100 = 57.14%.

This question belongs to: Maths Time and Work
Question #3
13 men can complete a work in 23 days. If 17 men work at the same rate, in how many days will the work be completed?
A. 21.59
B. 19.59
C. 23.59
D. 17.59

Correct Answer: Option D


Explanation:
Total work = 13 × 23 = 299 man-days. Required days = 299/17 = 17.59 days.

This question belongs to: Maths Time and Work