A and B work together. A alone can complete the work in 24 days and B alone in 32 days. What percentage of the total daily work is contributed by A? MCQ with Answer and Explanation

A and B work together. A alone can complete the work in 24 days and B alone in 32 days. What percentage of the total daily work is contributed by A?
A. 64.64
B. 62.14
C. 59.64
D. 57.14
Answer: Option D
Solution (By JKSSB Mock Tests)
A share = (1/24) / (1/24+1/32) ×100 = 57.14%.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
15 men can complete a work in 12 days. How many days will 18 men take to complete the same work?
A. 11 days
B. 10 days
C. 9 days
D. 8 days

Correct Answer: Option B


Explanation:
Using M1 * D1 = M2 * D2: 15 * 12 = 18 * D2 => 180 = 18 * D2 => D2 = 10 days.

This question belongs to: Maths Time and Work
Question #2
A can do a work in 13 days and B in 23 days. In how many days will they complete 75% of the work together?
A. 13.73
B. 8.73
C. 11.23
D. 6.23

Correct Answer: Option D


Explanation:
Combined time for full work multiplied by 0.75 = 6.23 days.

This question belongs to: Maths Time and Work
Question #3
A can complete a work in 24 days and B in 30 days. If both work together, in how many days will the work be completed?
A. 20.83
B. 18.33
C. 15.83
D. 13.33

Correct Answer: Option D


Explanation:
Combined rate = 1/24 + 1/30. Time = 13.33 days.

This question belongs to: Maths Time and Work