A and B work together. A alone can complete the work in 30 days and B alone in 26 days. What percentage of the total daily work is contributed by A? MCQ with Answer and Explanation

A and B work together. A alone can complete the work in 30 days and B alone in 26 days. What percentage of the total daily work is contributed by A?
A. 51.43
B. 46.43
C. 48.93
D. 53.93
Answer: Option B
Solution (By JKSSB Mock Tests)
A share = (1/30) / (1/30+1/26) ×100 = 46.43%.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
A and B can do a work in 12 days, B and C in 15 days, and C and A in 20 days. How many days will A alone take to finish the work?
A. 40 days
B. 60 days
C. 20 days
D. 30 days

Correct Answer: Option D


Explanation:
Total work = LCM(12, 15, 20) = 60 units. Efficiency of (A+B) = 5, (B+C) = 4, (C+A) = 3. Summing efficiencies gives 2*(A+B+C) = 12 => Efficiency of (A+B+C) = 6 units/day. Efficiency of A = (A+B+C) - (B+C) = 6 - 4 = 2 units/day. Time taken by A alone = 60 / 2 = 30 days.

This question belongs to: Maths Time and Work
Question #2
A can complete a work in 16 days and B can complete the same work in 16 days. If they work together, in how many days will the work be completed?
A. 14.0
B. 8.0
C. 10.0
D. 12.0

Correct Answer: Option B


Explanation:
Combined rate = 1/16 + 1/16. Time = 1 ÷ combined rate = 8.0 days.

This question belongs to: Maths Time and Work
Question #3
A can complete a work in 23 days and B can complete the same work in 23 days. If they work together, in how many days will the work be completed?
A. 17.5
B. 15.5
C. 11.5
D. 13.5

Correct Answer: Option C


Explanation:
Combined rate = 1/23 + 1/23. Time = 1 ÷ combined rate = 11.5 days.

This question belongs to: Maths Time and Work