A, B and C can complete a piece of work in 10, 15 and 20 days respectively. They started together but A left after 2 days and B left 2 days before the completion of the work. Find the total number of days taken to complete the work. MCQ with Answer and Explanation

A, B and C can complete a piece of work in 10, 15 and 20 days respectively. They started together but A left after 2 days and B left 2 days before the completion of the work. Find the total number of days taken to complete the work.
A. 8 days
B. 9 days
C. 7 days
D. 6 days
Answer: Option A
Solution (By JKSSB Mock Tests)
Total work = LCM(10, 15, 20) = 60 units. Efficiency of A = 6, B = 4, C = 3. Let the total work last for x days. A worked for 2 days, so work done = 2 * 6 = 12 units. Remaining work = 60 - 12 = 48 units. B worked for (x - 2) days and C worked for x days. Therefore, 4(x - 2) + 3x = 48 => 4x - 8 + 3x = 48 => 7x = 56 => x = 8 days.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
A can complete a work in 10 days and B can complete the same work in 30 days. If they work together, in how many days will the work be completed?
A. 9.5
B. 11.5
C. 13.5
D. 7.5

Correct Answer: Option D


Explanation:
Combined rate = 1/10 + 1/30. Time = 1 ÷ combined rate = 7.5 days.

This question belongs to: Maths Time and Work
Question #2
A and B can do a job in 12 days and 16 days respectively. Both work together for 3 days and then A leaves. How long will B take to complete the remaining work?
A. 9 days
B. 7 days
C. 8 days
D. 10 days

Correct Answer: Option A


Explanation:
Total work = LCM(12, 16) = 48 units. Efficiency of A = 4, B = 3. Combined efficiency = 7 units/day. In 3 days, work completed = 7 * 3 = 21 units. Remaining work = 48 - 21 = 27 units. Time taken by B for remaining work = 27 / 3 = 9 days.

This question belongs to: Maths Time and Work
Question #3
14 men can complete a work in 26 days. If 19 men work at the same rate, the work will be completed in:
A. 24.16
B. 34.16
C. 29.16
D. 19.16

Correct Answer: Option D


Explanation:
Total work = 364 man-days. Time = 364/19 = 19.16 days.

This question belongs to: Maths Time and Work