A, B and C can do a piece of work in 10, 12 and 15 days respectively. They began the work together but A left after 2 days and B left 3 days before the completion of the work. How long did the work last? MCQ with Answer and Explanation

A, B and C can do a piece of work in 10, 12 and 15 days respectively. They began the work together but A left after 2 days and B left 3 days before the completion of the work. How long did the work last?
A. 7 days
B. 5 days
C. 8 days
D. 6 days
Answer: Option A
Solution (By JKSSB Mock Tests)
Total work = LCM(10, 12, 15) = 60 units. Efficiency of A = 6, B = 5, C = 4. Let the total time be x days. A worked for 2 days. B worked for (x - 3) days. C worked for x days. Total work = 2*6 + (x - 3)*5 + x*4 = 60 => 12 + 5x - 15 + 4x = 60 => 9x - 3 = 60 => 9x = 63 => x = 7 days.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
A and B work together. A alone can complete the work in 30 days and B alone in 24 days. What percentage of the total daily work is contributed by A?
A. 49.44
B. 51.94
C. 44.44
D. 46.94

Correct Answer: Option C


Explanation:
A share = (1/30) / (1/30+1/24) ×100 = 44.44%.

This question belongs to: Maths Time and Work
Question #2
A can complete a work in 30 days. What percentage of work will A complete in 6 days?
A. 20.0
B. 25.0
C. 30.0
D. 35.0

Correct Answer: Option A


Explanation:
Percentage completed = (6/30) × 100 = 20.0%.

This question belongs to: Maths Time and Work
Question #3
A and B can do a piece of work in 12 days, B and C in 15 days, and C and A in 20 days. If A, B and C work together, in how many days will they complete the work?
A. 8 days
B. 10 days
C. 12 days
D. 5 days

Correct Answer: Option B


Explanation:
Total work = LCM(12, 15, 20) = 60 units. Efficiency of (A+B) = 5, (B+C) = 4, (C+A) = 3. Sum of efficiencies = 2 * (A+B+C) = 12 => Efficiency of (A+B+C) = 6 units/day. Time taken together = 60 / 6 = 10 days.

This question belongs to: Maths Time and Work