A can complete a work in 14 days and B in 37 days. If both work together, in how many days will the work be completed? MCQ with Answer and Explanation

A can complete a work in 14 days and B in 37 days. If both work together, in how many days will the work be completed?
A. 10.16
B. 15.16
C. 17.66
D. 12.66
Answer: Option A
Solution (By JKSSB Mock Tests)
Combined rate = 1/14 + 1/37. Time = 10.16 days.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
15 men can complete a work in 23 days. If 23 men work at the same rate, how many days are required?
A. 15.0
B. 17.5
C. 22.5
D. 20.0

Correct Answer: Option A


Explanation:
Total work = 345 man-days. Days = 15.0.

This question belongs to: Maths Time and Work
Question #2
A can do a piece of work in 80 days. He works at it for 10 days and then B alone finishes the remaining work in 42 days. In how many days can A and B together complete the work?
A. 30 days
B. 24 days
C. 35 days
D. 25 days

Correct Answer: Option A


Explanation:
Let total work be 80 units. Efficiency of A = 1 unit/day. In 10 days, A completes 10 units. Remaining work = 80 - 10 = 70 units. B finishes 70 units in 42 days, so B's efficiency = 70 / 42 = 5/3 units/day. Combined efficiency of A and B = 1 + 5/3 = 8/3 units/day. Time taken together = 80 / (8/3) = (80 * 3) / 8 = 30 days.

This question belongs to: Maths Time and Work
Question #3
If 8 men and 12 boys can finish a piece of work in 10 days, while 6 men and 8 boys can finish it in 14 days, find the time taken by 1 man alone to complete the work.
A. 160 days
B. 100 days
C. 140 days
D. 120 days

Correct Answer: Option C


Explanation:
Total work = 10 * (8M + 12B) = 14 * (6M + 8B) => 80M + 120B = 84M + 112B => 4M = 8B => 1M = 2B. Total work = 10 * (8M + 6M) = 140M. Thus, 1 man alone will take 140 days.

This question belongs to: Maths Time and Work