A can complete a work in 18 days and B in 19 days. If they work together, the work will be completed in:
A. 14.24
B. 9.24
C. 24.24
D. 19.24
Answer: Option B
Solution (By JKSSB Mock Tests)
Combined rate = 1/18 + 1/19. Required time = 9.24 days.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
A can complete a work in 14 days and B in 15 days. If they work together, the work will be completed in:
A. 12.24
B. 22.24
C. 17.24
D. 7.24

Correct Answer: Option D


Explanation:
Combined rate = 1/14 + 1/15. Required time = 7.24 days.

This question belongs to: Maths Time and Work
Question #2
A can do a piece of work in 20 days and B in 30 days. They work together for some time and then B leaves. If A completes the remaining work in 5 days, for how many days did they work together?
A. 10 days
B. 9 days
C. 8 days
D. 6 days

Correct Answer: Option B


Explanation:
Total work = LCM(20, 30) = 60 units. Efficiency of A = 3, B = 2. A worked alone for 5 days: work done = 5 * 3 = 15 units. Remaining work = 60 - 15 = 45 units. This was completed by A and B together. Combined efficiency = 3 + 2 = 5 units/day. Number of days they worked together = 45 / 5 = 9 days.

This question belongs to: Maths Time and Work
Question #3
15 men can complete a work in 19 days. If 19 men work at the same rate, in how many days will the work be completed?
A. 15.0
B. 17.0
C. 19.0
D. 21.0

Correct Answer: Option A


Explanation:
Total work = 15 × 19 = 285 man-days. Required days = 285/19 = 15.0 days.