Explanation:
3 Men = 5 Women => 6 Men = 10 Women. 6 men + 5 women = 10 women + 5 women = 15 women. Since 5 women take 12 days, 15 women will take (5 * 12) / 15 = 60 / 15 = 4 days.
12 men can complete a work in 4 days, while 15 women can complete the same work in 4 days. 6 men start working and after 2 days, all of them stop working. How many women should be put on the job to complete the remaining work in 3 days?