A can complete a work in 32 days and B in 19 days. If both work together, in how many days will the work be completed? MCQ with Answer and Explanation

A can complete a work in 32 days and B in 19 days. If both work together, in how many days will the work be completed?
A. 19.42
B. 16.92
C. 14.42
D. 11.92
Answer: Option D
Solution (By JKSSB Mock Tests)
Combined rate = 1/32 + 1/19. Time = 11.92 days.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
A can complete a work in 23 days and B in 21 days. If both work together, in how many days will the work be completed?
A. 10.98
B. 15.98
C. 18.48
D. 13.48

Correct Answer: Option A


Explanation:
Combined rate = 1/23 + 1/21. Time = 10.98 days.

This question belongs to: Maths Time and Work
Question #2
A is twice as fast as B. If A and B together can complete a piece of work in 8 days, in how many days can A alone complete it?
A. 24 days
B. 10 days
C. 16 days
D. 12 days

Correct Answer: Option D


Explanation:
Let efficiency of B = 1, then efficiency of A = 2. Combined efficiency = 3 units/day. Total work = 8 * 3 = 24 units. Time taken by A alone = 24 / 2 = 12 days.

This question belongs to: Maths Time and Work
Question #3
A can complete a work in 23 days. What percentage of the work will be completed in 7 days?
A. 37.93
B. 30.43
C. 32.93
D. 35.43

Correct Answer: Option B


Explanation:
Completed percentage = (7/23)×100 = 30.43%.

This question belongs to: Maths Time and Work