A can do a piece of work in 10 days, B in 15 days. They work together for 2 days and then A leaves. In how many days will B complete the remaining work?
A. 8 days
B. 10 days
C. 12 days
D. 11 days
Answer: Option B
Solution (By JKSSB Mock Tests)
Total work = LCM(10, 15) = 30 units. Efficiency of A = 3, B = 2. Combined efficiency = 5 units/day. In 2 days, work completed = 2 * 5 = 10 units. Remaining work = 30 - 10 = 20 units. Time taken by B to complete remaining work = 20 / 2 = 10 days.