A can do a work in 18 days and B in 28 days. They work together for 5 days. What percentage of work remains? MCQ with Answer and Explanation

A can do a work in 18 days and B in 28 days. They work together for 5 days. What percentage of work remains?
A. 64.37
B. 59.37
C. 54.37
D. 69.37
Answer: Option C
Solution (By JKSSB Mock Tests)
Remaining work = (1 - 5*(1/18+1/28)) ×100 = 54.37%.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
12 men can complete a work in 16 days. If 16 men work at the same rate, in how many days will the work be completed?
A. 18.0
B. 14.0
C. 12.0
D. 16.0

Correct Answer: Option C


Explanation:
Total work = 12 × 16 = 192 man-days. Required days = 192/16 = 12.0 days.

This question belongs to: Maths Time and Work
Question #2
A and B work together. A alone can complete the work in 30 days and B alone in 26 days. What percentage of the total daily work is contributed by A?
A. 53.93
B. 46.43
C. 51.43
D. 48.93

Correct Answer: Option B


Explanation:
A share = (1/30) / (1/30+1/26) ×100 = 46.43%.

This question belongs to: Maths Time and Work
Question #3
A can complete a work in 10 days and B in 27 days. If they work together, the work will be completed in:
A. 7.3
B. 12.3
C. 17.3
D. 22.3

Correct Answer: Option A


Explanation:
Combined rate = 1/10 + 1/27. Required time = 7.3 days.

This question belongs to: Maths Time and Work