A can finish a work in 12 days and B can do it in 15 days. After A had worked for 3 days, B also joined him to finish the remaining work. In how many days was the remaining work completed? MCQ with Answer and Explanation

A can finish a work in 12 days and B can do it in 15 days. After A had worked for 3 days, B also joined him to finish the remaining work. In how many days was the remaining work completed?
A. 3 days
B. 6 days
C. 4 days
D. 5 days
Answer: Option D
Solution (By JKSSB Mock Tests)
Total work = LCM(12, 15) = 60 units. Efficiency of A = 5, B = 4. In 3 days, A completed 3 * 5 = 15 units. Remaining work = 60 - 15 = 45 units. Combined efficiency of A and B = 5 + 4 = 9 units/day. Time taken for remaining work = 45 / 9 = 5 days.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
A can complete a work in 30 days and B in 36 days. If both work together, in how many days will the work be completed?
A. 18.86
B. 23.86
C. 21.36
D. 16.36

Correct Answer: Option D


Explanation:
Combined rate = 1/30 + 1/36. Time = 16.36 days.

This question belongs to: Maths Time and Work
Question #2
8 men can complete a work in 12 days. If 12 men work at the same rate, in how many days will the work be completed?
A. 8.0
B. 10.0
C. 14.0
D. 12.0

Correct Answer: Option A


Explanation:
Total work = 8 × 12 = 96 man-days. Required days = 96/12 = 8.0 days.

This question belongs to: Maths Time and Work
Question #3
15 men can complete a work in 22 days. If 20 men work at the same rate, the work will be completed in:
A. 31.5
B. 16.5
C. 21.5
D. 26.5

Correct Answer: Option B


Explanation:
Total work = 330 man-days. Time = 330/20 = 16.5 days.