A can finish a work in 12 days and B can do it in 15 days. After A had worked for 3 days, B also joined him to finish the remaining work. In how many days was the remaining work completed? MCQ with Answer and Explanation
A can finish a work in 12 days and B can do it in 15 days. After A had worked for 3 days, B also joined him to finish the remaining work. In how many days was the remaining work completed?
A. 3 days
B. 6 days
C. 4 days
D. 5 days
Answer: Option D
Solution (By JKSSB Mock Tests)
Total work = LCM(12, 15) = 60 units. Efficiency of A = 5, B = 4. In 3 days, A completed 3 * 5 = 15 units. Remaining work = 60 - 15 = 45 units. Combined efficiency of A and B = 5 + 4 = 9 units/day. Time taken for remaining work = 45 / 9 = 5 days.