A can finish a work in 18 days and B can do the same work in half the time taken by A. Then, working together, what part of the same work can they finish in a day? MCQ with Answer and Explanation

A can finish a work in 18 days and B can do the same work in half the time taken by A. Then, working together, what part of the same work can they finish in a day?
A. 2/5
B. 1/9
C. 1/4
D. 1/6
Answer: Option D
Solution (By JKSSB Mock Tests)
Time taken by A = 18 days, so B takes 9 days. Efficiency of A = 1/18, B = 1/9. Together in one day = 1/18 + 1/9 = 3/18 = 1/6.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
A and B can complete a work in 12 days and 16 days respectively. Both work together for 3 days and then A leaves. How long will B take to complete the remaining work?
A. 8 days
B. 11 days
C. 9 days
D. 10 days

Correct Answer: Option C


Explanation:
Total work = LCM(12, 16) = 48 units. Efficiency of A = 4, B = 3. Combined efficiency = 7 units/day. In 3 days, work completed = 3 * 7 = 21 units. Remaining work = 48 - 21 = 27 units. Time taken by B to complete remaining work = 27 / 3 = 9 days.

This question belongs to: Maths Time and Work
Question #2
A can complete a work in 18 days and B in 39 days. If both work together, in how many days will the work be completed?
A. 17.32
B. 19.82
C. 14.82
D. 12.32

Correct Answer: Option D


Explanation:
Combined rate = 1/18 + 1/39. Time = 12.32 days.

This question belongs to: Maths Time and Work
Question #3
A can complete a work in 10 days and B in 19 days. If they work together, the work will be completed in:
A. 16.55
B. 21.55
C. 11.55
D. 6.55

Correct Answer: Option D


Explanation:
Combined rate = 1/10 + 1/19. Required time = 6.55 days.

This question belongs to: Maths Time and Work