A is 25% more efficient than B. If they working together can finish a work in 20 days, then in how many days can B alone finish it? MCQ with Answer and Explanation

A is 25% more efficient than B. If they working together can finish a work in 20 days, then in how many days can B alone finish it?
A. 40 days
B. 36 days
C. 45 days
D. 50 days
Answer: Option C
Solution (By JKSSB Mock Tests)
Let efficiency of B = 4, then efficiency of A = 5. Combined efficiency = 9 units/day. Total work = 20 * 9 = 180 units. Time taken by B alone = 180 / 4 = 45 days.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
A can complete a work in 17 days and B can complete the same work in 32 days. If they work together, in how many days will the work be completed?
A. 15.1
B. 17.1
C. 11.1
D. 13.1

Correct Answer: Option C


Explanation:
Combined rate = 1/17 + 1/32. Time = 1 ÷ combined rate = 11.1 days.

This question belongs to: Maths Time and Work
Question #2
A can complete a work in 15 days and B in 26 days. If they work together, the work will be completed in:
A. 24.51
B. 14.51
C. 9.51
D. 19.51

Correct Answer: Option C


Explanation:
Combined rate = 1/15 + 1/26. Required time = 9.51 days.

This question belongs to: Maths Time and Work
Question #3
A can complete a work in 19 days and B in 19 days. If they work together, the work will be completed in:
A. 9.5
B. 24.5
C. 14.5
D. 19.5

Correct Answer: Option A


Explanation:
Combined rate = 1/19 + 1/19. Required time = 9.5 days.

This question belongs to: Maths Time and Work