A can complete a work in 19 days and B in 19 days. If they work together, the work will be completed in: MCQ with Answer and Explanation

A can complete a work in 19 days and B in 19 days. If they work together, the work will be completed in:
A. 19.5
B. 24.5
C. 9.5
D. 14.5
Answer: Option C
Solution (By JKSSB Mock Tests)
Combined rate = 1/19 + 1/19. Required time = 9.5 days.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
A is twice as fast as B and B is twice as fast as C. If they together can complete a work in 4 days, in how many days can C alone complete it?
A. 28 days
B. 32 days
C. 16 days
D. 24 days

Correct Answer: Option A


Explanation:
Let efficiency of C = 1, then B = 2 and A = 4. Combined efficiency = 1 + 2 + 4 = 7 units/day. Total work = 4 * 7 = 28 units. Time taken by C alone = 28 / 1 = 28 days.

This question belongs to: Maths Time and Work
Question #2
A can complete a work in 11 days and B in 22 days. After working together for 5 days, what percentage of work remains?
A. 31.82
B. 34.32
C. 36.82
D. 39.32

Correct Answer: Option A


Explanation:
Remaining work = (1 - 5*(1/11+1/22))×100 = 31.82%.

This question belongs to: Maths Time and Work
Question #3
A and B work together. A alone can complete the work in 24 days and B alone in 32 days. What percentage of the total daily work is contributed by A?
A. 62.14
B. 57.14
C. 64.64
D. 59.64

Correct Answer: Option B


Explanation:
A share = (1/24) / (1/24+1/32) ×100 = 57.14%.

This question belongs to: Maths Time and Work