A can finish a work in 20 days and B in 30 days. They work together for 7 days and then both leave. Then C alone finishes the remaining work in 10 days. In how many days can C alone finish the full work?
Explanation:
Total work = LCM(20, 30) = 60 units. Efficiency of A = 3, B = 2. Combined efficiency = 5 units/day. In 7 days, work completed = 7 * 5 = 35 units. Remaining work = 60 - 35 = 25 units. C takes 10 days to do 25 units, so efficiency of C = 25 / 10 = 2.5 units/day. Time taken by C alone for full work = 60 / 2.5 = 24 days.
A can complete a piece of work in 14 days and B in 21 days. They begin together but A leaves 3 days before the completion of the work. Find the total number of days taken to complete the work.
Explanation:
Total work = LCM(14, 21) = 42 units. Efficiency of A = 3, B = 2. Let total days be x. A works for (x - 3) days, B works for x days. 3(x - 3) + 2x = 42 => 3x - 9 + 2x = 42 => 5x = 51 => x = 51/5 = 10(1/5) days.
No comments yet. Be the first to start the discussion!