A can complete a piece of work in 14 days and B in 21 days. They begin together but A leaves 3 days before the completion of the work. Find the total number of days taken to complete the work. MCQ with Answer and Explanation

A can complete a piece of work in 14 days and B in 21 days. They begin together but A leaves 3 days before the completion of the work. Find the total number of days taken to complete the work.
A. 10(1/5) days
B. 9(1/5) days
C. 11 days
D. 8(3/5) days
Answer: Option A
Solution (By JKSSB Mock Tests)
Total work = LCM(14, 21) = 42 units. Efficiency of A = 3, B = 2. Let total days be x. A works for (x - 3) days, B works for x days. 3(x - 3) + 2x = 42 => 3x - 9 + 2x = 42 => 5x = 51 => x = 51/5 = 10(1/5) days.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
A, B and C can do a piece of work in 10, 12 and 15 days respectively. They began the work together but A left after 2 days and B left 3 days before the completion of the work. How long did the work last?
A. 6 days
B. 8 days
C. 7 days
D. 5 days

Correct Answer: Option C


Explanation:
Total work = LCM(10, 12, 15) = 60 units. Efficiency of A = 6, B = 5, C = 4. Let the total time be x days. A worked for 2 days. B worked for (x - 3) days. C worked for x days. Total work = 2*6 + (x - 3)*5 + x*4 = 60 => 12 + 5x - 15 + 4x = 60 => 9x - 3 = 60 => 9x = 63 => x = 7 days.

This question belongs to: Maths Time and Work
Question #2
A and B can complete a work in 10 days and 15 days respectively. They started together, but A left after some days and B finished the remaining work in 5 days. After how many days did A leave?
A. 5 days
B. 2 days
C. 4 days
D. 3 days

Correct Answer: Option C


Explanation:
Total work = LCM(10, 15) = 30 units. Efficiency of A = 3, B = 2. B worked alone for 5 days: work done = 5 * 2 = 10 units. Remaining work = 30 - 10 = 20 units. This was completed by A and B together. Combined efficiency = 3 + 2 = 5 units/day. Time they worked together = 20 / 5 = 4 days. Thus, A left after 4 days.

This question belongs to: Maths Time and Work
Question #3
15 men can complete a work in 19 days. If 19 men work at the same rate, in how many days will the work be completed?
A. 15.0
B. 19.0
C. 17.0
D. 21.0

Correct Answer: Option A


Explanation:
Total work = 15 × 19 = 285 man-days. Required days = 285/19 = 15.0 days.

This question belongs to: Maths Time and Work