A can complete a piece of work in 14 days and B in 21 days. They begin together but A leaves 3 days before the completion of the work. Find the total number of days taken to complete the work. MCQ with Answer and Explanation

A can complete a piece of work in 14 days and B in 21 days. They begin together but A leaves 3 days before the completion of the work. Find the total number of days taken to complete the work.
A. 9(1/5) days
B. 11 days
C. 8(3/5) days
D. 10(1/5) days
Answer: Option D
Solution (By JKSSB Mock Tests)
Total work = LCM(14, 21) = 42 units. Efficiency of A = 3, B = 2. Let total days be x. A works for (x - 3) days, B works for x days. 3(x - 3) + 2x = 42 => 3x - 9 + 2x = 42 => 5x = 51 => x = 51/5 = 10(1/5) days.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
A can complete a work in 22 days and B can complete the same work in 32 days. If they work together, in how many days will the work be completed?
A. 15.04
B. 17.04
C. 13.04
D. 19.04

Correct Answer: Option C


Explanation:
Combined rate = 1/22 + 1/32. Time = 1 ÷ combined rate = 13.04 days.

This question belongs to: Maths Time and Work
Question #2
A can complete a work in 11 days and B can complete the same work in 31 days. If they work together, in how many days will the work be completed?
A. 10.12
B. 14.12
C. 8.12
D. 12.12

Correct Answer: Option C


Explanation:
Combined rate = 1/11 + 1/31. Time = 1 ÷ combined rate = 8.12 days.

This question belongs to: Maths Time and Work
Question #3
14 men can complete a work in 26 days. If 19 men work at the same rate, the work will be completed in:
A. 34.16
B. 24.16
C. 19.16
D. 29.16

Correct Answer: Option C


Explanation:
Total work = 364 man-days. Time = 364/19 = 19.16 days.

This question belongs to: Maths Time and Work