12 men can complete a project in 8 days. How many extra men are required to complete the same project in 6 days?
A. 8
B. 6
C. 16
D. 4
Answer: Option D
Solution (By JKSSB Mock Tests)
Using M1 * D1 = M2 * D2: 12 * 8 = M2 * 6. M2 = 96 / 6 = 16 men. Extra men required = 16 - 12 = 4.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
A can complete a work in 19 days and B in 41 days. If both work together, in how many days will the work be completed?
A. 20.48
B. 17.98
C. 15.48
D. 12.98

Correct Answer: Option D


Explanation:
Combined rate = 1/19 + 1/41. Time = 12.98 days.

This question belongs to: Maths Time and Work
Question #2
A is 50% more efficient than B. C does half of the work done by A and B together in the same time. If C alone can do the work in 30 days, then A, B and C together can do the work in:
A. 15 days
B. 10 days
C. 12 days
D. 20 days

Correct Answer: Option B


Explanation:
Let efficiency of B = 2, then efficiency of A = 3. Combined efficiency of A and B = 5. Efficiency of C = 5 / 2 = 2.5. Total work = Efficiency of C * Time of C = 2.5 * 30 = 75 units. Combined efficiency of A, B and C = 3 + 2 + 2.5 = 7.5 units/day. Time taken together = 75 / 7.5 = 10 days.

This question belongs to: Maths Time and Work
Question #3
A can complete a work in 24 days and B in 18 days. If they work together, the work will be completed in:
A. 25.29
B. 20.29
C. 15.29
D. 10.29

Correct Answer: Option D


Explanation:
Combined rate = 1/24 + 1/18. Required time = 10.29 days.

This question belongs to: Maths Time and Work