A and B can do a piece of work in 15 days and 10 days respectively. They started the work together, but A left after 2 days. In how many days will B complete the remaining work? MCQ with Answer and Explanation

A and B can do a piece of work in 15 days and 10 days respectively. They started the work together, but A left after 2 days. In how many days will B complete the remaining work?
A. 7 days
B. 6 days
C. 5 days
D. 6(2/3) days
Answer: Option D
Solution (By JKSSB Mock Tests)
Total work = LCM(15, 10) = 30 units. Efficiency of A = 2, B = 3. Combined efficiency = 5. In 2 days, work done = 2 * 5 = 10 units. Remaining work = 30 - 10 = 20 units. Time taken by B to complete remaining work = 20 / 3 = 6(2/3) days.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
A can complete a work in 20 days. What percentage of the work will be completed in 7 days?
A. 37.5
B. 40.0
C. 35.0
D. 42.5

Correct Answer: Option C


Explanation:
Completed percentage = (7/20)×100 = 35.0%.

This question belongs to: Maths Time and Work
Question #2
12 men can complete a work in 8 days. How many days will it take for 16 men to complete the same work?
A. 7 days
B. 4 days
C. 6 days
D. 5 days

Correct Answer: Option C


Explanation:
Using M1 * D1 = M2 * D2: 12 * 8 = 16 * D2. 96 = 16 * D2. D2 = 96 / 16 = 6 days.

This question belongs to: Maths Time and Work
Question #3
A is twice as fast as B and B is thrice as fast as C. If C alone can complete the work in 24 days, in how many days can they together finish the work?
A. 2.6 days
B. 2.4 days
C. 3 days
D. 4 days

Correct Answer: Option B


Explanation:
Let efficiency of C = 1. Then efficiency of B = 3 * 1 = 3. Efficiency of A = 2 * 3 = 6. Total work = Efficiency of C * Time of C = 1 * 24 = 24 units. Combined efficiency of A, B and C = 6 + 3 + 1 = 10. Time taken together = 24 / 10 = 2.4 days.

This question belongs to: Maths Time and Work