A, B and C can do a work in 20, 30 and 60 days respectively. In how many days can A do the work if he is assisted by B and C on every third day? MCQ with Answer and Explanation

A, B and C can do a work in 20, 30 and 60 days respectively. In how many days can A do the work if he is assisted by B and C on every third day?
A. 15 days
B. 12 days
C. 18 days
D. 16 days
Answer: Option A
Solution (By JKSSB Mock Tests)
Total work = LCM(20, 30, 60) = 60 units. Efficiency of A = 3, B = 2, C = 1. Day 1: A works (3 units). Day 2: A works (3 units). Day 3: A, B, and C work together (3 + 2 + 1 = 6 units). Total work in 3 days = 3 + 3 + 6 = 12 units. To complete 60 units, number of 3-day cycles needed = 60 / 12 = 5 cycles. Total days = 5 * 3 = 15 days.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
A can complete a work in 20 days and B can complete the same work in 15 days. If they work together, in how many days will the work be completed?
A. 8.57
B. 10.57
C. 12.57
D. 14.57

Correct Answer: Option A


Explanation:
Combined rate = 1/20 + 1/15. Time = 1 ÷ combined rate = 8.57 days.

This question belongs to: Maths Time and Work
Question #2
A can complete a work in 14 days and B in 37 days. If both work together, in how many days will the work be completed?
A. 12.66
B. 17.66
C. 15.16
D. 10.16

Correct Answer: Option D


Explanation:
Combined rate = 1/14 + 1/37. Time = 10.16 days.

This question belongs to: Maths Time and Work
Question #3
A and B work together. A alone can complete the work in 30 days and B alone in 26 days. What percentage of the total daily work is contributed by A?
A. 51.43
B. 46.43
C. 53.93
D. 48.93

Correct Answer: Option B


Explanation:
A share = (1/30) / (1/30+1/26) ×100 = 46.43%.

This question belongs to: Maths Time and Work