A can complete a work in 13 days and B can complete the same work in 33 days. If they work together, in how many days will the work be completed? MCQ with Answer and Explanation

A can complete a work in 13 days and B can complete the same work in 33 days. If they work together, in how many days will the work be completed?
A. 9.33
B. 11.33
C. 15.33
D. 13.33
Answer: Option A
Solution (By JKSSB Mock Tests)
Combined rate = 1/13 + 1/33. Time = 1 ÷ combined rate = 9.33 days.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
A and B can complete a work in 12 days and 16 days respectively. Both work together for 3 days and then A leaves. How long will B take to complete the remaining work?
A. 10 days
B. 11 days
C. 9 days
D. 8 days

Correct Answer: Option C


Explanation:
Total work = LCM(12, 16) = 48 units. Efficiency of A = 4, B = 3. Combined efficiency = 7 units/day. In 3 days, work completed = 3 * 7 = 21 units. Remaining work = 48 - 21 = 27 units. Time taken by B to complete remaining work = 27 / 3 = 9 days.

This question belongs to: Maths Time and Work
Question #2
A and B together can do a piece of work in 6 days. If A alone can do it in 18 days, in how many days can B alone complete the work?
A. 15 days
B. 9 days
C. 20 days
D. 12 days

Correct Answer: Option B


Explanation:
Combined 1-day work = 1/6. A's 1-day work = 1/18. B's 1-day work = 1/6 - 1/18 = 2/18 = 1/9. Therefore, B alone can complete the work in 9 days.

This question belongs to: Maths Time and Work
Question #3
A, B and C can complete a piece of work in 10, 12 and 15 days respectively. They started together but A left 2 days after the start and B left 3 days before the completion of the work. How long did the work last?
A. 7 days
B. 5 days
C. 8 days
D. 6 days

Correct Answer: Option A


Explanation:
Total work = LCM(10, 12, 15) = 60 units. Efficiency of A = 6, B = 5, C = 4. Let total days be x. A works for 2 days. B works for (x - 3) days. C works for x days. Total work = 2*6 + (x - 3)*5 + 4*x = 60 => 12 + 5x - 15 + 4x = 60 => 9x - 3 = 60 => 9x = 63 => x = 7 days.

This question belongs to: Maths Time and Work