A can complete a work in 27 days and B in 44 days. If both work together, in how many days will the work be completed? MCQ with Answer and Explanation

A can complete a work in 27 days and B in 44 days. If both work together, in how many days will the work be completed?
A. 19.23
B. 24.23
C. 21.73
D. 16.73
Answer: Option D
Solution (By JKSSB Mock Tests)
Combined rate = 1/27 + 1/44. Time = 16.73 days.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
A can complete a project in 20 days and B in 30 days. If they work on alternate days starting with A, in how many days will the project be completed?
A. 26 days
B. 22 days
C. 24 days
D. 25 days

Correct Answer: Option C


Explanation:
Total work = LCM(20, 30) = 60 units. Efficiency of A = 3, B = 2. In a 2-day cycle (A then B), work completed = 3 + 2 = 5 units. Number of cycles required = 60 / 5 = 12 cycles. Total time = 12 * 2 = 24 days.

This question belongs to: Maths Time and Work
Question #2
31 men can complete a work in 29 days. If 39 men work at the same rate, how many days are required?
A. 28.05
B. 30.55
C. 25.55
D. 23.05

Correct Answer: Option D


Explanation:
Total work = 899 man-days. Days = 23.05.

This question belongs to: Maths Time and Work
Question #3
A and B can do a piece of work in 12 days, B and C in 15 days, and C and A in 20 days. In how many days can B alone complete the work?
A. 20 days
B. 30 days
C. 40 days
D. 60 days

Correct Answer: Option A


Explanation:
Total work = LCM(12, 15, 20) = 60 units. Efficiency of (A+B) = 5, (B+C) = 4, (C+A) = 3. Summing efficiencies gives 2*(A+B+C) = 12 => Efficiency of (A+B+C) = 6. Efficiency of B = (A+B+C) - (C+A) = 6 - 3 = 3. Time taken by B alone = 60 / 3 = 20 days.

This question belongs to: Maths Time and Work