A can complete a work in 34 days and B in 45 days. If both work together, in how many days will the work be completed? MCQ with Answer and Explanation

A can complete a work in 34 days and B in 45 days. If both work together, in how many days will the work be completed?
A. 21.87
B. 24.37
C. 19.37
D. 26.87
Answer: Option C
Solution (By JKSSB Mock Tests)
Combined rate = 1/34 + 1/45. Time = 19.37 days.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
A is 25% more efficient than B. If they working together can finish a work in 20 days, then in how many days can B alone finish it?
A. 45 days
B. 36 days
C. 40 days
D. 50 days

Correct Answer: Option A


Explanation:
Let efficiency of B = 4, then efficiency of A = 5. Combined efficiency = 9 units/day. Total work = 20 * 9 = 180 units. Time taken by B alone = 180 / 4 = 45 days.

This question belongs to: Maths Time and Work
Question #2
A and B can complete a work together in 15 days. They work together for 3 days, then A leaves. If B alone completes the remaining work in 16 days, in how many days can A alone complete the whole work?
A. 45 days
B. 60 days
C. 30 days
D. 75 days

Correct Answer: Option B


Explanation:
Let the total work be 60 units. Combined efficiency of A and B = 60 / 15 = 4 units/day. In 3 days, they complete 3 * 4 = 12 units. Remaining work = 60 - 12 = 48 units. B completes 48 units in 16 days, so B's efficiency = 48 / 16 = 3 units/day. A's efficiency = 4 - 3 = 1 unit/day. Time taken by A alone = 60 / 1 = 60 days.

This question belongs to: Maths Time and Work
Question #3
25 men can complete a work in 23 days. If 33 men work at the same rate, how many days are required?
A. 22.42
B. 17.42
C. 24.92
D. 19.92

Correct Answer: Option B


Explanation:
Total work = 575 man-days. Days = 17.42.

This question belongs to: Maths Time and Work