A can do a work in 11 days and B in 29 days. In how many days will they complete 75% of the work together? MCQ with Answer and Explanation

A can do a work in 11 days and B in 29 days. In how many days will they complete 75% of the work together?
A. 10.98
B. 5.98
C. 13.48
D. 8.48
Answer: Option B
Solution (By JKSSB Mock Tests)
Combined time for full work multiplied by 0.75 = 5.98 days.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
15 men can complete a work in 22 days. If 20 men work at the same rate, the work will be completed in:
A. 21.5
B. 16.5
C. 26.5
D. 31.5

Correct Answer: Option B


Explanation:
Total work = 330 man-days. Time = 330/20 = 16.5 days.

This question belongs to: Maths Time and Work
Question #2
Three pumps working 8 hours a day can empty a tank in 2 days. How many hours a day must 4 pumps work to empty the same tank in 1 day?
A. 10 hours
B. 12 hours
C. 16 hours
D. 15 hours

Correct Answer: Option B


Explanation:
Using P1 * D1 * H1 = P2 * D2 * H2: 3 * 2 * 8 = 4 * 1 * H2 => 48 = 4 * H2 => H2 = 12 hours.

This question belongs to: Maths Time and Work
Question #3
A can complete a work in 26 days and B in 52 days. After working together for 5 days, what percentage of work remains?
A. 78.65
B. 76.15
C. 71.15
D. 73.65

Correct Answer: Option C


Explanation:
Remaining work = (1 - 5*(1/26+1/52))×100 = 71.15%.

This question belongs to: Maths Time and Work