A is 50% more efficient than B. C does half of the work done by A and B together in the same time. If C alone can do the work in 40 days, then A, B and C together can do the work in: MCQ with Answer and Explanation

A is 50% more efficient than B. C does half of the work done by A and B together in the same time. If C alone can do the work in 40 days, then A, B and C together can do the work in:
A. 30 days
B. 15 days
C. 13(1/3) days
D. 20 days
Answer: Option C
Solution (By JKSSB Mock Tests)
Let efficiency of B = 2, then efficiency of A = 3. Combined efficiency of A and B = 5. Efficiency of C = 5 / 2 = 2.5. Total work = Efficiency of C * Time taken by C = 2.5 * 40 = 100 units. Combined efficiency of A, B and C = 3 + 2 + 2.5 = 7.5 units/day. Time taken together = 100 / 7.5 = 1000 / 75 = 40 / 3 = 13(1/3) days.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
A can do a work in 11 days and B in 23 days. In how many days will they complete 75% of the work together?
A. 5.58
B. 8.08
C. 13.08
D. 10.58

Correct Answer: Option A


Explanation:
Combined time for full work multiplied by 0.75 = 5.58 days.

This question belongs to: Maths Time and Work
Question #2
A can complete a work in 23 days and B in 46 days. After working together for 5 days, what percentage of work remains?
A. 69.89
B. 72.39
C. 74.89
D. 67.39

Correct Answer: Option D


Explanation:
Remaining work = (1 - 5*(1/23+1/46))×100 = 67.39%.

This question belongs to: Maths Time and Work
Question #3
A can complete a work in 22 days and B can complete the same work in 22 days. If they work together, in how many days will the work be completed?
A. 13.0
B. 11.0
C. 17.0
D. 15.0

Correct Answer: Option B


Explanation:
Combined rate = 1/22 + 1/22. Time = 1 ÷ combined rate = 11.0 days.

This question belongs to: Maths Time and Work