A team of 30 men is supposed to do a work in 38 days. After 25 days, 5 more men were employed and the work was finished one day earlier than the scheduled time. How many days would it have been delayed if 5 more men were not employed? MCQ with Answer and Explanation

A team of 30 men is supposed to do a work in 38 days. After 25 days, 5 more men were employed and the work was finished one day earlier than the scheduled time. How many days would it have been delayed if 5 more men were not employed?
A. 2 days
B. 4 days
C. 1 day
D. 3 days
Answer: Option C
Solution (By JKSSB Mock Tests)
Scheduled time = 38 days. Work finished 1 day earlier, so it took 37 days. For the first 25 days, 30 men worked. For the remaining 37 - 25 = 12 days, 35 men worked. Remaining work = 35 * 12 = 420 man-days. If 5 extra men were not joined, 30 men would take 420 / 30 = 14 days to complete this remaining work. Total days taken without extra men = 25 + 14 = 39 days. Delay = 39 - 38 = 1 day.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
A can complete a work in 20 days and B in 30 days. They start together but A leaves after 4 days. In how many total days will the work be completed?
A. 25 days
B. 24 days
C. 16 days
D. 20 days

Correct Answer: Option B


Explanation:
Total work = LCM(20, 30) = 60 units. Efficiency of A = 3, B = 2. In 4 days, work completed = 4 * (3 + 2) = 20 units. Remaining work = 60 - 20 = 40 units. Time taken by B to finish remaining work = 40 / 2 = 20 days. Total days = 4 + 20 = 24 days.

This question belongs to: Maths Time and Work
Question #2
A can do a certain work in the same time in which B and C together can do it. If A and B together could do it in 10 days and C alone in 50 days, then B alone could do it in:
A. 25 days
B. 35 days
C. 30 days
D. 20 days

Correct Answer: Option A


Explanation:
Total work = LCM(10, 50) = 50 units. Efficiency of (A + B) = 5, efficiency of C = 1. Total efficiency of (A + B + C) = 5 + 1 = 6. Given A = B + C. So, (B + C) + B + C = 6 => 2(B + C) = 6 => B + C = 3. Since C = 1, B = 2. Time taken by B alone = 50 / 2 = 25 days.

This question belongs to: Maths Time and Work
Question #3
11 men can complete a work in 15 days. If 15 men work at the same rate, in how many days will the work be completed?
A. 11.0
B. 15.0
C. 17.0
D. 13.0

Correct Answer: Option A


Explanation:
Total work = 11 × 15 = 165 man-days. Required days = 165/15 = 11.0 days.

This question belongs to: Maths Time and Work