If 10 men can complete a project in 12 days, how many more men are required to finish it in 8 days? MCQ with Answer and Explanation

If 10 men can complete a project in 12 days, how many more men are required to finish it in 8 days?
A. 5
B. 6
C. 4
D. 8
Answer: Option A
Solution (By JKSSB Mock Tests)
Using M1 * D1 = M2 * D2: 10 * 12 = M2 * 8 => 120 = 8 * M2 => M2 = 15 men. More men required = 15 - 10 = 5.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
A can complete a piece of work in 18 days, B in 24 days and C in 36 days. If they work together, in how many days will they finish the work?
A. 9 days
B. 8 days
C. 6 days
D. 7 days

Correct Answer: Option B


Explanation:
Total work = LCM(18, 24, 36) = 72 units. Efficiency of A = 4, B = 3, C = 2. Combined efficiency = 4 + 3 + 2 = 9 units/day. Time taken together = 72 / 9 = 8 days.

This question belongs to: Maths Time and Work
Question #2
A can complete a work in 24 days and B in 30 days. If both work together, in how many days will the work be completed?
A. 13.33
B. 18.33
C. 15.83
D. 20.83

Correct Answer: Option A


Explanation:
Combined rate = 1/24 + 1/30. Time = 13.33 days.

This question belongs to: Maths Time and Work
Question #3
A can complete a work in 17 days and B can complete the same work in 32 days. If they work together, in how many days will the work be completed?
A. 11.1
B. 13.1
C. 15.1
D. 17.1

Correct Answer: Option A


Explanation:
Combined rate = 1/17 + 1/32. Time = 1 ÷ combined rate = 11.1 days.

This question belongs to: Maths Time and Work