If 10 men can complete a project in 12 days, how many more men are required to finish it in 8 days? MCQ with Answer and Explanation

If 10 men can complete a project in 12 days, how many more men are required to finish it in 8 days?
A. 6
B. 4
C. 5
D. 8
Answer: Option C
Solution (By JKSSB Mock Tests)
Using M1 * D1 = M2 * D2: 10 * 12 = M2 * 8 => 120 = 8 * M2 => M2 = 15 men. More men required = 15 - 10 = 5.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
A can finish a work in 20 days and B in 30 days. They work together for 7 days and then both leave. Then C alone finishes the remaining work in 10 days. In how many days can C alone finish the full work?
A. 30 days
B. 25 days
C. 20 days
D. 24 days

Correct Answer: Option D


Explanation:
Total work = LCM(20, 30) = 60 units. Efficiency of A = 3, B = 2. Combined efficiency = 5 units/day. In 7 days, work completed = 7 * 5 = 35 units. Remaining work = 60 - 35 = 25 units. C takes 10 days to do 25 units, so efficiency of C = 25 / 10 = 2.5 units/day. Time taken by C alone for full work = 60 / 2.5 = 24 days.

This question belongs to: Maths Time and Work
Question #2
A and B work together. A alone can complete the work in 18 days and B alone in 24 days. What percentage of the total daily work is contributed by A?
A. 64.64
B. 62.14
C. 57.14
D. 59.64

Correct Answer: Option C


Explanation:
A share = (1/18) / (1/18+1/24) ×100 = 57.14%.

This question belongs to: Maths Time and Work
Question #3
X can do a piece of work in 40 days. He works at it for 8 days and then Y alone finishes the remaining work in 16 days. How long will X and Y together take to complete the work?
A. 16 days
B. 15 days
C. 13(1/3) days
D. 14 days

Correct Answer: Option C


Explanation:
Let total work be 40 units. Efficiency of X = 1 unit/day. In 8 days, X completes 8 units. Remaining work = 40 - 8 = 32 units. Y finishes 32 units in 16 days, so Y's efficiency = 32 / 16 = 2 units/day. Combined efficiency of X and Y = 1 + 2 = 3 units/day. Time taken together = 40 / 3 = 13(1/3) days.

This question belongs to: Maths Time and Work