A and B can do a piece of work in 45 days and 40 days respectively. They began the work together, but A left after some days and B finished the remaining work in 23 days. After how many days did A leave? MCQ with Answer and Explanation

A and B can do a piece of work in 45 days and 40 days respectively. They began the work together, but A left after some days and B finished the remaining work in 23 days. After how many days did A leave?
A. 9 days
B. 12 days
C. 8 days
D. 6 days
Answer: Option A
Solution (By JKSSB Mock Tests)
Total work = LCM(45, 40) = 360 units. Efficiency of A = 8, B = 9. B worked alone for 23 days, so work done = 23 * 9 = 207 units. Remaining work = 360 - 207 = 153 units. This was completed by A and B together. Combined efficiency = 8 + 9 = 17. Time worked together = 153 / 17 = 9 days. Thus, A left after 9 days.

Discuss this Question (0)

No comments yet. Be the first to start the discussion!

Practice More Time and Work Questions

Question #1
A can finish a work in 18 days and B can do the same work in 15 days. B worked for 10 days and left the job. In how many days can A alone finish the remaining work?
A. 5 days
B. 5(1/2) days
C. 6 days
D. 8 days

Correct Answer: Option C


Explanation:
Total work = LCM(18, 15) = 90 units. Efficiency of A = 5, B = 6. B works for 10 days: work done = 10 * 6 = 60 units. Remaining work = 90 - 60 = 30 units. Time taken by A to finish the remaining work = 30 / 5 = 6 days.

This question belongs to: Maths Time and Work
Question #2
A can complete a work in 21 days and B in 42 days. After working together for 5 days, what percentage of work remains?
A. 66.79
B. 64.29
C. 69.29
D. 71.79

Correct Answer: Option B


Explanation:
Remaining work = (1 - 5*(1/21+1/42))×100 = 64.29%.

This question belongs to: Maths Time and Work
Question #3
13 men can complete a work in 17 days. If 17 men work at the same rate, in how many days will the work be completed?
A. 15.0
B. 13.0
C. 17.0
D. 19.0

Correct Answer: Option B


Explanation:
Total work = 13 × 17 = 221 man-days. Required days = 221/17 = 13.0 days.

This question belongs to: Maths Time and Work