Question #361
19 men can complete a work in 32 days. If 27 men work at the same rate, how many days are required?
A. 25.02
B. 22.52
C. 30.02
D. 27.52

Correct Answer: Option B


Explanation:
Total work = 608 man-days. Days = 22.52.

This question belongs to: Maths Time and Work
Question #362
A and B work together. A alone can complete the work in 24 days and B alone in 36 days. What percentage of the total daily work is contributed by A?
A. 60.0
B. 67.5
C. 65.0
D. 62.5

Correct Answer: Option A


Explanation:
A share = (1/24) / (1/24+1/36) ×100 = 60.0%.

This question belongs to: Maths Time and Work
Question #363
A can do a work in 13 days and B in 23 days. In how many days will they complete 75% of the work together?
A. 6.23
B. 11.23
C. 8.73
D. 13.73

Correct Answer: Option A


Explanation:
Combined time for full work multiplied by 0.75 = 6.23 days.

This question belongs to: Maths Time and Work
Question #364
A can complete a work in 14 days and B in 37 days. If both work together, in how many days will the work be completed?
A. 12.66
B. 10.16
C. 15.16
D. 17.66

Correct Answer: Option B


Explanation:
Combined rate = 1/14 + 1/37. Time = 10.16 days.

This question belongs to: Maths Time and Work
Question #365
A can complete a work in 25 days and B in 50 days. After working together for 5 days, what percentage of work remains?
A. 70.0
B. 72.5
C. 75.0
D. 77.5

Correct Answer: Option A


Explanation:
Remaining work = (1 - 5*(1/25+1/50))×100 = 70.0%.

This question belongs to: Maths Time and Work
Question #366
25 men can complete a work in 23 days. If 33 men work at the same rate, how many days are required?
A. 22.42
B. 19.92
C. 24.92
D. 17.42

Correct Answer: Option D


Explanation:
Total work = 575 man-days. Days = 17.42.

This question belongs to: Maths Time and Work
Question #367
A and B work together. A alone can complete the work in 30 days and B alone in 26 days. What percentage of the total daily work is contributed by A?
A. 46.43
B. 53.93
C. 48.93
D. 51.43

Correct Answer: Option A


Explanation:
A share = (1/30) / (1/30+1/26) ×100 = 46.43%.

This question belongs to: Maths Time and Work
Question #368
A can do a work in 19 days and B in 29 days. In how many days will they complete 75% of the work together?
A. 16.11
B. 11.11
C. 13.61
D. 8.61

Correct Answer: Option D


Explanation:
Combined time for full work multiplied by 0.75 = 8.61 days.

This question belongs to: Maths Time and Work
Question #369
A can complete a work in 20 days and B in 43 days. If both work together, in how many days will the work be completed?
A. 21.15
B. 13.65
C. 18.65
D. 16.15

Correct Answer: Option B


Explanation:
Combined rate = 1/20 + 1/43. Time = 13.65 days.

This question belongs to: Maths Time and Work
Question #370
A can complete a work in 14 days and B in 28 days. After working together for 5 days, what percentage of work remains?
A. 46.43
B. 53.93
C. 48.93
D. 51.43

Correct Answer: Option A


Explanation:
Remaining work = (1 - 5*(1/14+1/28))×100 = 46.43%.

This question belongs to: Maths Time and Work
Question #371
31 men can complete a work in 29 days. If 39 men work at the same rate, how many days are required?
A. 23.05
B. 30.55
C. 28.05
D. 25.55

Correct Answer: Option A


Explanation:
Total work = 899 man-days. Days = 23.05.

This question belongs to: Maths Time and Work
Question #372
A and B work together. A alone can complete the work in 18 days and B alone in 32 days. What percentage of the total daily work is contributed by A?
A. 64.0
B. 66.5
C. 69.0
D. 71.5

Correct Answer: Option A


Explanation:
A share = (1/18) / (1/18+1/32) ×100 = 64.0%.

This question belongs to: Maths Time and Work
Question #373
A can do a work in 11 days and B in 17 days. In how many days will they complete 75% of the work together?
A. 7.51
B. 10.01
C. 12.51
D. 5.01

Correct Answer: Option D


Explanation:
Combined time for full work multiplied by 0.75 = 5.01 days.

This question belongs to: Maths Time and Work
Question #374
A can complete a work in 26 days and B in 20 days. If both work together, in how many days will the work be completed?
A. 16.3
B. 13.8
C. 18.8
D. 11.3

Correct Answer: Option D


Explanation:
Combined rate = 1/26 + 1/20. Time = 11.3 days.

This question belongs to: Maths Time and Work
Question #375
A can complete a work in 20 days and B in 40 days. After working together for 5 days, what percentage of work remains?
A. 67.5
B. 62.5
C. 65.0
D. 70.0

Correct Answer: Option B


Explanation:
Remaining work = (1 - 5*(1/20+1/40))×100 = 62.5%.

This question belongs to: Maths Time and Work
Question #376
A and B work together. A alone can complete the work in 24 days and B alone in 22 days. What percentage of the total daily work is contributed by A?
A. 47.83
B. 52.83
C. 50.33
D. 55.33

Correct Answer: Option A


Explanation:
A share = (1/24) / (1/24+1/22) ×100 = 47.83%.

This question belongs to: Maths Time and Work
Question #377
A can do a work in 17 days and B in 23 days. In how many days will they complete 75% of the work together?
A. 14.83
B. 9.83
C. 7.33
D. 12.33

Correct Answer: Option C


Explanation:
Combined time for full work multiplied by 0.75 = 7.33 days.

This question belongs to: Maths Time and Work
Question #378
A can complete a work in 32 days and B in 26 days. If both work together, in how many days will the work be completed?
A. 14.34
B. 19.34
C. 16.84
D. 21.84

Correct Answer: Option A


Explanation:
Combined rate = 1/32 + 1/26. Time = 14.34 days.

This question belongs to: Maths Time and Work
Question #379
A can complete a work in 26 days and B in 52 days. After working together for 5 days, what percentage of work remains?
A. 78.65
B. 73.65
C. 71.15
D. 76.15

Correct Answer: Option C


Explanation:
Remaining work = (1 - 5*(1/26+1/52))×100 = 71.15%.

This question belongs to: Maths Time and Work
Question #380
A and B work together. A alone can complete the work in 30 days and B alone in 28 days. What percentage of the total daily work is contributed by A?
A. 55.78
B. 50.78
C. 53.28
D. 48.28

Correct Answer: Option D


Explanation:
A share = (1/30) / (1/30+1/28) ×100 = 48.28%.

This question belongs to: Maths Time and Work