Time and Work MCQs

Maths

Time and Work MCQs

Practice Time and Work MCQs with answers and detailed solutions. Learn work efficiency, pipes and cisterns, men and women work problems, partnership, wages, productivity and advanced aptitude questions commonly asked in competitive exams.

446
Total Questions

Practice Questions

Page 12 of 23
Question #221
13 men can complete a work in 17 days. If 17 men work at the same rate, in how many days will the work be completed?
A. 17.0
B. 19.0
C. 13.0
D. 15.0

Correct Answer: Option C


Explanation:
Total work = 13 × 17 = 221 man-days. Required days = 221/17 = 13.0 days.

This question belongs to: Maths Time and Work
Question #222
14 men can complete a work in 18 days. If 18 men work at the same rate, in how many days will the work be completed?
A. 14.0
B. 18.0
C. 16.0
D. 20.0

Correct Answer: Option A


Explanation:
Total work = 14 × 18 = 252 man-days. Required days = 252/18 = 14.0 days.

This question belongs to: Maths Time and Work
Question #223
15 men can complete a work in 19 days. If 19 men work at the same rate, in how many days will the work be completed?
A. 15.0
B. 17.0
C. 21.0
D. 19.0

Correct Answer: Option A


Explanation:
Total work = 15 × 19 = 285 man-days. Required days = 285/19 = 15.0 days.

This question belongs to: Maths Time and Work
Question #224
16 men can complete a work in 20 days. If 20 men work at the same rate, in how many days will the work be completed?
A. 16.0
B. 20.0
C. 22.0
D. 18.0

Correct Answer: Option A


Explanation:
Total work = 16 × 20 = 320 man-days. Required days = 320/20 = 16.0 days.

This question belongs to: Maths Time and Work
Question #225
17 men can complete a work in 21 days. If 21 men work at the same rate, in how many days will the work be completed?
A. 23.0
B. 19.0
C. 21.0
D. 17.0

Correct Answer: Option D


Explanation:
Total work = 17 × 21 = 357 man-days. Required days = 357/21 = 17.0 days.

This question belongs to: Maths Time and Work
Question #226
18 men can complete a work in 22 days. If 22 men work at the same rate, in how many days will the work be completed?
A. 24.0
B. 18.0
C. 20.0
D. 22.0

Correct Answer: Option B


Explanation:
Total work = 18 × 22 = 396 man-days. Required days = 396/22 = 18.0 days.

This question belongs to: Maths Time and Work
Question #227
19 men can complete a work in 23 days. If 23 men work at the same rate, in how many days will the work be completed?
A. 25.0
B. 19.0
C. 21.0
D. 23.0

Correct Answer: Option B


Explanation:
Total work = 19 × 23 = 437 man-days. Required days = 437/23 = 19.0 days.

This question belongs to: Maths Time and Work
Question #228
8 men can complete a work in 24 days. If 12 men work at the same rate, in how many days will the work be completed?
A. 18.0
B. 20.0
C. 22.0
D. 16.0

Correct Answer: Option D


Explanation:
Total work = 8 × 24 = 192 man-days. Required days = 192/12 = 16.0 days.

This question belongs to: Maths Time and Work
Question #229
9 men can complete a work in 25 days. If 13 men work at the same rate, in how many days will the work be completed?
A. 21.31
B. 19.31
C. 17.31
D. 23.31

Correct Answer: Option C


Explanation:
Total work = 9 × 25 = 225 man-days. Required days = 225/13 = 17.31 days.

This question belongs to: Maths Time and Work
Question #230
10 men can complete a work in 26 days. If 14 men work at the same rate, in how many days will the work be completed?
A. 20.57
B. 18.57
C. 22.57
D. 24.57

Correct Answer: Option B


Explanation:
Total work = 10 × 26 = 260 man-days. Required days = 260/14 = 18.57 days.

This question belongs to: Maths Time and Work
Question #231
11 men can complete a work in 27 days. If 15 men work at the same rate, in how many days will the work be completed?
A. 21.8
B. 25.8
C. 19.8
D. 23.8

Correct Answer: Option C


Explanation:
Total work = 11 × 27 = 297 man-days. Required days = 297/15 = 19.8 days.

This question belongs to: Maths Time and Work
Question #232
12 men can complete a work in 28 days. If 16 men work at the same rate, in how many days will the work be completed?
A. 27.0
B. 21.0
C. 25.0
D. 23.0

Correct Answer: Option B


Explanation:
Total work = 12 × 28 = 336 man-days. Required days = 336/16 = 21.0 days.

This question belongs to: Maths Time and Work
Question #233
13 men can complete a work in 29 days. If 17 men work at the same rate, in how many days will the work be completed?
A. 24.18
B. 26.18
C. 28.18
D. 22.18

Correct Answer: Option D


Explanation:
Total work = 13 × 29 = 377 man-days. Required days = 377/17 = 22.18 days.

This question belongs to: Maths Time and Work
Question #234
14 men can complete a work in 12 days. If 18 men work at the same rate, in how many days will the work be completed?
A. 13.33
B. 9.33
C. 15.33
D. 11.33

Correct Answer: Option B


Explanation:
Total work = 14 × 12 = 168 man-days. Required days = 168/18 = 9.33 days.

This question belongs to: Maths Time and Work
Question #235
15 men can complete a work in 13 days. If 19 men work at the same rate, in how many days will the work be completed?
A. 14.26
B. 12.26
C. 10.26
D. 16.26

Correct Answer: Option C


Explanation:
Total work = 15 × 13 = 195 man-days. Required days = 195/19 = 10.26 days.

This question belongs to: Maths Time and Work
Question #236
16 men can complete a work in 14 days. If 20 men work at the same rate, in how many days will the work be completed?
A. 13.2
B. 15.2
C. 11.2
D. 17.2

Correct Answer: Option C


Explanation:
Total work = 16 × 14 = 224 man-days. Required days = 224/20 = 11.2 days.

This question belongs to: Maths Time and Work
Question #237
17 men can complete a work in 15 days. If 21 men work at the same rate, in how many days will the work be completed?
A. 14.14
B. 12.14
C. 16.14
D. 18.14

Correct Answer: Option B


Explanation:
Total work = 17 × 15 = 255 man-days. Required days = 255/21 = 12.14 days.

This question belongs to: Maths Time and Work
Question #238
18 men can complete a work in 16 days. If 22 men work at the same rate, in how many days will the work be completed?
A. 19.09
B. 17.09
C. 13.09
D. 15.09

Correct Answer: Option C


Explanation:
Total work = 18 × 16 = 288 man-days. Required days = 288/22 = 13.09 days.

This question belongs to: Maths Time and Work
Question #239
19 men can complete a work in 17 days. If 23 men work at the same rate, in how many days will the work be completed?
A. 20.04
B. 14.04
C. 16.04
D. 18.04

Correct Answer: Option B


Explanation:
Total work = 19 × 17 = 323 man-days. Required days = 323/23 = 14.04 days.

This question belongs to: Maths Time and Work
Question #240
8 men can complete a work in 18 days. If 12 men work at the same rate, in how many days will the work be completed?
A. 14.0
B. 12.0
C. 18.0
D. 16.0

Correct Answer: Option B


Explanation:
Total work = 8 × 18 = 144 man-days. Required days = 144/12 = 12.0 days.

This question belongs to: Maths Time and Work